Road Closure Information

Road Closure Information
Posted on 07/16/2018
Road Closure Information

Police detail schedule Monday, July 16

  • Chestnut Street and Forest Street
  • 35 Afterglow Way
  • Myrtle Avenue and Orange Avenue
  • Walnut Street and Claremont Avenue

PSE&G Projects

For information regarding PSE&G gas work in Montclair, please visit the PSE&G We're working in your town web page.

Township Road Construction

Project Start: Monday, July 16 (weather permitting)

  • James Street from Park Street to Central Avenue

Project Start: Monday, July 9 (weather permitting)

  • Road construction on Forest Street from Chestnut Street to Walnut Street (curbing - 3 to 4 weeks)

Project Start: Monday, July 2 (weather permitting)

  • Road construction on Forest Street from the dead end of Forest Street to Chestnut Street (curbing - 3 to 4 weeks)

Township Sewer Lining Project

North American Pipeline (NAP) continues the trenchless lining installation process in the areas cited below. Hours of operation are 8:00 PM to 6:00 AM Monday through Thursday. Temporary partial lane closures are expected in order to provide sufficient working areas for necessary equipment.>

The following schedule has been provided by NAP; additional updates will be provided as they are received.

Grove Street

Thursday, July 5

  • NAP will not be on site

Friday, July 6

  • NAP will not be on site

Please note that NAP will not be in Montclair for the week of July 8 to July 14. NAP anticipates to return to Montclair the week of July 15 to July 21.