Montclair Township Water Main Replacement Project

Montclair Township Water Main Replacement Project
Posted on 07/12/2021
 Montclair Township Water Main Replacement Project  Generate Name

NOTICE TO RESIDENTS

Please be advised that water main construction will begin on Thursday, July 8, 2021. There may be limited access to your driveway during construction hours. Additional notices will be sent out in the event of any water service interruptions.

If you have any questions, please contact someone from the construction team listed below. Any other questions after 5:00 p.m., please contact the Montclair Water Bureau at 973-744-4600.

John Garcia Construction Co. – John Garcia, 973-390-3728
H2M Architects & Engineers – Abbas Turab, 201-983-2086

Water Bureau Project Schedule 

Construction Schedule-Oakcroft Avenue Area

  • Construction Layout and Coordination: 7/6/21-7/8/21
  • Mobilization and Site Preparation: 7/8/21-7/9/21
  • Tie in on Brookfield Rd & Oakcroft Ave: 7/12/21
  • Water Main on Brookfield Rd: 7 /13/21- 7 /14/21
  • Water Main on Oakcroft Ave: 7 /15/21- 7 /28/21
  • Water Main on Parkside: 7 /29/21- 8/5/21
  • Tie In on North Mountain Ave.: 8/5/21
  • Water Main on Godfrey Rd.: 8/6/21-8/18/21
  • Tie in on North Mountain Ave.: 8/19/21
  • Water Main on Princeton Pl, Edgemont Rd and Carteret St.: 8/20/21
  • 8/26/21
  • Water Services: 8/27 /21- 9/10/21
  • Tie in on Princeton Pl, Edgemont Rd and Carteret St.: 9/13/21-9/17 /21
  • Site Restoration: 9/20/21-9/21/21

Note: Dates may vary due to unforeseen utility conflicts & weather related issues